Why Has It Taken So Long? An Honest Look at Our Journey

Nov 11
3 min read

Updated: 9 hours ago

If you supported the Win a House and Car draw in 2021, you may have wondered: why, several years later, are we still working towards our new grounds?

It is a fair question. You backed this project because you wanted to help provide a permanent home for Athenry Camogie Club. You deserve to understand what has happened since.

The journey has involved a lengthy search for suitable land, a planning refusal and an alternative location requiring a proposed land swap. Much of that work has happened behind the scenes, without visible changes on the ground.

Here is what brought us to the planning milestone announced in March 2026.

First, we needed the right land

After the draw generated €693,000 in net funds, the committee needed to identify a suitable site.

The land had to meet several requirements: enough space for pitches and supporting facilities, an accessible location close to Athenry, an affordable price and a reasonable prospect of securing planning permission.

During 2022, the committee approached more than 20 landowners. Finding land that met those needs took time.

In April 2023, a 25-acre site at Moonbaun was purchased. It was a significant step forward.

Then came a major setback

Planning permission for the Moonbaun site was refused in November 2023.

That decision meant the project could not proceed there as intended. After the fundraising effort, the search and the purchase, the committee had to work towards another route.

For supporters waiting to see pitches taking shape, this helps explain a substantial part of the delay. The work completed up to that point had not delivered a site where the planned development could go ahead.

A new location brought a different process

In 2024, an alternative site was identified on Teagasc lands adjacent to Athenry town.

Progressing this opportunity involved engagement with the Department of Agriculture, Food and the Marine around a proposed land swap involving the Moonbaun lands.

Written permission allowed the club to apply for planning permission on the alternative site as a preliminary step. However, permission to submit a planning application did not mean that the land swap was complete.

Planning and land arrangements were separate parts of the process, both requiring work.

Preparing the application took further work

A development of this scale requires professional reports, drawings and supporting documentation.

During 2025, approximately €100,000 was invested in planning preparation and professional reports. The application was submitted to Galway County Council in December.

These steps do not produce the visible progress of machinery arriving or pitches being laid. They are, however, part of establishing whether and how the development can proceed.

March 2026 marked an important breakthrough

Planning permission was granted in March 2026.

After the earlier refusal and the work to progress an alternative site, this was a major milestone. It brought the project closer to delivery.

It did not complete every step. The May 2026 committee update recorded that the proposed land swap remained in progress, while development costings and funding options were being prepared.

Why couldn’t building begin straight after the draw?

The draw provided the financial foundation to begin the journey. It did not provide a site with planning permission or the full funding needed to complete the development.

The project has required several connected pieces to come together: suitable land, planning permission, tenure, detailed costings and a funding package.

When planning was refused at Moonbaun, the route to delivery changed. The alternative opportunity then brought its own land arrangements and planning work.

That is why the time since the draw cannot be measured in construction progress alone.

Your patience deserves clear updates

We understand that supporters want to see a return on the trust they placed in this project. Years of preparation can feel frustrating when there are still no grounds to show for it.

This website gives us a place to explain completed milestones, share setbacks and distinguish the work still underway from what has been secured.

Our commitment remains the same: to work towards dedicated facilities for Athenry Camogie Club and a lasting benefit for future generations.

Thank you for helping us get this far. Your support made the first steps possible, and you deserve to stay informed as the journey continues.

This article reflects the project milestones recorded in the Facility Development Committee’s May 2026 update.

 
 
 